Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) – Accelerated Irrigation Benefit Programme (AIBP)

During 2016-17, among ninety nine (99) ongoing Major/Medium Irrigation Projects of the Country under PMKSY-AIBP, having ultimate irrigation potential of 76.03 lakh hectare and balance cost of Rs. 77595.00 crore, the following 03 projects of UT of J&K were prioritized for completion in phases upto December, 2019 along with their Command Area Development and Water Management (CADWM) works:-

S.No Project Name Targeted IP (Ha.) District Benefitted Status
1 Tral Lift Irrigation Scheme 5122 Pulwama Targeted 2020-21
2 Restoration & modernization of Main Ravi canal 15016 Jammu, Samba, Kathua Targeted 2020-21
3 Rajpora Lift Irrigation Scheme 2429 Pulwama Completed

Financial and physical details of these projects are as under:

Financial Details
Total No. of Schemes 3
Approved cost (Rs. In Crore) 289.20
Cumulative expenditure ending 03/2020 (Rs. In Crore) 272.70
Balance cost as on 01.4.2020 (Rs. In Crore) 16.50
Funds released during 2020-21:
Central Share (Rs. In Crore) 9.50
UT Share (Rs. In Crore) 0.00
Physical Details:
Schemes physical completed ending 03/2020 (Nos.) 01
Schemes targeted during 2020-21 (Nos.) 02
Ultimate Irrigation Potential Target (In Th. Hectare) 59.18
Irrigation Potential achieved ending 03/2020 (In Th. Hectare) 21110
Irrigation Potential Targeted 2020-21 (In Hectare) 1458