Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) – Accelerated Irrigation Benefit Programme (AIBP)
During 2016-17, among ninety nine (99) ongoing Major/Medium Irrigation Projects of the Country under PMKSY-AIBP, having ultimate irrigation potential of 76.03 lakh hectare and balance cost of Rs. 77595.00 crore, the following 03 projects of UT of J&K were prioritized for completion in phases upto December, 2019 along with their Command Area Development and Water Management (CADWM) works:-
S.No | Project Name | Targeted IP
(Ha.) | District Benefitted |
Status |
1 | Tral Lift Irrigation Scheme | 5122 | Pulwama | Targeted 2020-21 |
2 | Restoration & modernization of Main Ravi canal | 15016 | Jammu, Samba, Kathua | Targeted 2020-21 |
3 | Rajpora Lift Irrigation Scheme | 2429 | Pulwama | Completed |
Financial and physical details of these projects are as under:
Financial Details | |
Total No. of Schemes | 3
|
Approved cost (Rs. In Crore) | 289.20
|
Cumulative expenditure ending 03/2020 (Rs. In Crore) | 272.70
|
Balance cost as on 01.4.2020 (Rs. In Crore) | 16.50
|
Funds released during 2020-21: | |
Central Share (Rs. In Crore) | 9.50 |
UT Share (Rs. In Crore) | 0.00 |
Physical Details: | |
Schemes physical completed ending 03/2020 (Nos.) | 01 |
Schemes targeted during 2020-21 (Nos.) | 02 |
Ultimate Irrigation Potential Target (In Th. Hectare) | 59.18 |
Irrigation Potential achieved ending 03/2020 (In Th. Hectare) | 21110 |
Irrigation Potential Targeted 2020-21 (In Hectare) | 1458 |